Widgetized Section

Go to Admin » Appearance » Widgets » and move Gabfire Widget: Social into that MastheadOverlay zone

Campaigners worry as campus plans fall behind schedule

WILTSHIRE Council has fallen behind the timeline given for the development of the Melksham Campus, raising concern for a local group who say the latest update is ‘worrying’.

According to the timeline given to the community at the Melksham Area Board meeting in October, the ‘final design concept’ for the new campus was expected to be completed by the end of March.

At the area board meeting in February, after announcing that the campus plans were ‘moving ahead and on time’, Wiltshire cllr John Thomson said that he hoped to present the final design to the area board in April.

However, at the meeting held earlier this month, the update read out to those in attendance said that architects were working with the council and stakeholders to ‘advance the detailed designs with a view to submitting the planning application later this year’.

When asked by Melksham News for an update on the progress on the design and when it will be ready, a Wiltshire Council spokesperson said, “We are working closely with architects and stakeholders on final details for Melksham Community Campus. The extended design team is now being appointed so that final designs can be developed. The detailed designs will continue to change as they are developed, but when a final scheme is arrived at, this will of course be shared with the local community through the area board.”

In response, a member of the campus community monitoring group, Colin Goodhind said, “It is good to see progress on some issues, but the apparent delay in completion of the final design concept and the vagueness of the explanation at this ‘early’ stage is worrying.

“This deviation from the timeline announced back in October is exactly the sort of thing that the campus watch group was set up to look out for and we will be requesting more information on this.

“The community wants to feel it’s being kept properly informed but being told that ‘when a final scheme is arrived at, this will of course be shared with the local community through the area board’ does not do this.

“The announcement back in October produced a new air of optimism about the project but the ‘blurring’ of key issues is bringing back memories of the past few years. Hopefully meaningful reassurance will be forthcoming soon.”

The update given at the area board meeting said, “Melksham House site: The architects DKA have been reappointed and are working with the council and stakeholders to advance the detailed designs with a view to submitting the planning application later this year, as per the programme (submitted October 2017).

“The council have sought pre-application advice on the residential element and how this element of the project will complement the campus.

“To accelerate and enable work to start on the site; the following is under way:An upgrade at the A350 entrance adjacent to the cemetery to make it suitable for construction traffic to enter; Removal of asbestos and demolition of redundant outbuildings; Infrastructure for tennis floodlights; Completion of all pre-construction surveys; Removal of redundant signage and the installation of hoardings.

“Outdoor bowls: The council has undertaken works to the outdoor bowls facility. These works were vital to separate the club’s infrastructure from Melksham House and allow the club to operate independently of the council. The works will conclude mid-April.

“Tennis Club: The council is out to tender for a contractor to resurface four tennis courts. Depending on the tender returns, the expectation is that this work will be complete by mid-summer. This work was due to take place as part of the main campus build, but has been advanced due to the poor state of the existing courts.

“Canberra: Legal advice has been sought and the council will arrange to meet with Young Melksham to discuss the next steps.”

Wiltshire Council’s Estimated Timeline from October 2017

• Final design concept – OVERDUE

• Cost plan 1  March – April 2018

• Update surveys  Feb – Jun 2018

• Developed design and Planning information  April – July 2018

• Cost plan 2  June – July 2018

• Wiltshire review scheme: Final sign-off  June – July 2018

• Planning  July 2018 – Jan 2019

• OJEU process tender Main contractor  Oct 2018 – April 2019

• Review and Award of contract  April – June 2019

• Mobilisation period  June 2019

• Construction commences  July 2019

• 18-month build process  Until Jan 21

3 Responses to Campaigners worry as campus plans fall behind schedule

  1. W.gaisford

    April 25, 2018 at 4:33 pm

    With all the excuses being made will the campus ever be built? Are the council running out money due to the ongoing costs of architects etc?

  2. Writecustomessays

    April 26, 2018 at 6:52 am

    Let”s assume three things. The Turnbull government goes the limit and has an election in November, 2019. (If a week is a long a time in politics, 18 months is off the charts.) Being a councillor in Alice does not qualify as an office of profit under the Crown. (If a mayor and councillor in Tasmania doesn”t, how could a different standard apply in the NT?) Jacinta defeats Warren. (I still think that”s a big ask as winning his elections is just about all Warren has ever done, and he has consistently done that very well.) So now we”re looking at Jacinta winning a Federal seat in November, 2019. Before resigning from Council, she seeks legal advice to determine if she can hold down both jobs. This takes us into December after Council has risen for the summer break. Council reconvenes at the end of January, 2020. At the request of Council, Jacinta asks for another month to realise her accumulated leave and to further consider her position. Having done so, she resigns from Council in February, 2020. That takes us into the 18 month cut-off for a by-election, hence no by-election needed. End of drama. View Comment

  3. emp3z

    April 29, 2018 at 11:00 pm

    Nice blog here! Additionally your website so much up fast! What web host are you the use of? Can I get your associate hyperlink for your host? I desire my web site loaded up as quickly as yours lol.

Leave a Reply

Your email address will not be published. Required fields are marked *